
Fasikan
In 2023, SCA acquired the permitted wind power project Fasikan Vind AB from Arise AB. The project is located on SCA-owned land in Bräcke Municipality, Jämtland County.
The project includes the construction of 15 turbines that will be delivered by Nordex. The total installed power will be 105 MW with an estimated production of 333 GWh, which corresponds to an annual consumption of electricity for approximately 15,000 households.
Arise AB is responsible for construction of the wind farm, which will begin in November 2023 and the park is expected to be in operation at the beginning of 2026.
Facts - Fasikan
| Technology: | Wind power |
|---|---|
| Phase: | Under construction |
| Turbines: | 15 pcs |
| Tipheight: | Max 240 m |
| Annual production: | 333 GWh |
Project update
In 2024, the first of two construction phases for the Fasikan Wind Farm was carried out.
In this phase, 15 turbine locations were completed, including foundations and crane pads for installation. The internal road and electrical network were also finalized. During the autumn, the roads were tested to ensure they could safely and efficiently handle the required transports.
In parallel, work was ongoing in autumn 2024 and winter 2025 to construct the new power line between Fasikan and the connection point to the regional grid in Ånge.
The final kilometers of the line were placed underground to minimize environmental impact.
In spring 2025, transportation of wind turbine components to the site began, and by the end of May, the first turbine was erected. Construction continues through summer and autumn 2025. For safety reasons, work is paused during periods of high wind or thunderstorm risk.
During the most intense phases of construction, up to 100 people may be present on-site at Fasikan simultaneously.
For safety reasons, access to the area may be restricted during lifting and transport operations. We kindly ask for your understanding and thank local residents for their patience and consideration during the construction period.
The Fasikan Wind Farm is scheduled to be commissioned at the turn of the year 2025/2026.
Last updated: August 2025
Development of the Fasikan Wind Farm
Winter 2024 – Stable roads and turning areas are being constructed for upcoming wind power transports.Photographer: Torbjörn Bergkvist

July 2024 – Construction of the foundation for one of the 15 wind turbines to be erected in Fasikan.Photographer: Torbjörn Bergkvist

January 2025 – Components for the new wind turbines are unloaded at Tunadalshamnen.Photographer: Torbjörn Bergkvist

January 2025 – Transporting wind turbine components requires careful planning and precision.Photographer: Torbjörn Bergkvist

Two cranes and wind turbine components are visible from above.Photographer: Torbjörn Bergkvist

July 2025 – To install the wind turbine, wind speeds must not exceed 7 m/s. Here, a tower section is lifted into place.Photographer: Torbjörn Bergkvist

July 2025 – The drivetrain is installed in the nacelle. The drivetrain consists of a gearbox and generator, where the wind energy is converted into electricity.Photographer: Torbjörn Bergkvist

July 2025 – The hub is lifted into position on the wind turbine. The three blades are then mounted on the hub. Working at heights requires strict safety measures and fearless workers.Photographer: Torbjörn Bergkvist

September 2025 – One of the wind turbine blades is lifted into position and secured to the hub.Photographer: Torbjörn Bergkvist

September 2025 – The 15 wind turbines are planned to be operational and generating renewable electricity at the beginning of 2026.Photographer: Torbjörn Bergkvist

Winter 2024 – Stable roads and turning areas are being constructed for upcoming wind power transports.Photographer: Torbjörn Bergkvist
Contacts













